Producers with a connection power requirement of more than 8 MW or Customers (Consumers) with a connection power demand of more than 12 MVA
Under the applicable Transmission and Distribution Rules, Generators with a requested connection power greater than 8 MW or Customers (Consumers) with a requested connection power greater than 12 MVA, interested in connecting to the Transmission/Distribution System, need to submit a Connection Request to the Cyprus Transmission System Operator (CTSO).
Cyprus Energy Regulatory Authority (CERA) in its decision 821/2012 dated at 30/11/2012, approved the "Procedure for the Connection Agreement between the TSO and the Applicant (Producer / Customer)" and the "Basic Principles of Billing Policy for Connections to the System of Transmission and Distribution of RES Producers, Conventional Producers and Customers ", with effect from 01/01/2013. These texts include several elements concerning the Capital
Expenditure of the Connection, as well as other financial obligations of the Applicant.
For more information on New Connections in the Transmission System , please visit the
Cyprus Transmission System Operator (CTSO).
Producers with a requested connection power of up to 8 MW or Customers (Consumers) with a requested connection power of up to 12 MVA
Under the applicable Transmission and Distribution Rules, Producers with a requested connection power of up to 8 MW or Customers (Consumers) with a requested connection power of up to 12 MVA, interested in connecting to the Transmission/Distribution System, need to submit a Connection Request to the Distribution System Operator (EAC).
CERA, through the Regulatory Decision 03/2013, decided to approve the new EAC Charge Policy for Connection to the Distribution System. This regulatory decision can be found in the Legislation section.
For more information on New Connections in the Distribution System visit the
Cyprus Electricity Authority (EAC) website