The Exemption constitutes a simplified licensing regime for electricity generation stations using conventional fuels for own use.
Scope
The exemption applies to the construction and operation of electricity generation stations using conventional fuels, with an electrical capacity greater than 30 kW up to 1 MW, for own use.
Submission of Application
Applications are submitted exclusively through
CERA’s Electronic Application Submission Portal.
Examination Procedure and Grant of Exemption
The procedure is governed by the Electricity Market Regulation Law and the Electricity Market Regulation (Issuance of Licences) Regulations. Detailed information on the steps for submission, examination and grant of the exemption is provided in the Frequently Asked Questions.
The Standard Terms of the exemption are available at the bottom of the page.
Application Fee
The application fee is paid through the Portal upon submission. The date of registration of the application in CERA’s register and the assignment of a serial number are determined by the date of payment, in accordance with the Electricity Market Regulation (Licence Fees) Regulations.
Annual Fees
Annual fees are paid each year for the maintenance of the licence in force.
For the applicable amounts, refer to the Licensing – Licence Fees page and the Frequently Asked Questions.